Selling UOM is different from B.UOM for Configurable product
Hi Experts, Need your help on the following scenario we have. We have a configurable product which has the following characteristics. It has Base UOM as KG and selling unit of measure as PCs. So when a...
View Articlewhy material is blocked but in the co11n can confirme and post good movment...
Hi every body.we set the material status for blocked but production users can create production order for them and confirm it and post goods issue ??why it is possible??
View Articlematerial planning via Production version
Hi,Experts I'm trying to Plan and Produce a SINGLE material with regards to TWO routings. I'm 90percent certain that Prod Versions can do that.. Bom will remain same in both routings, only routings...
View ArticleSpecify version of component
Hi, Is there a possibility to specify a production version of component in the BOM. For example: I have FERT F01 and F2 and in both is included the same SEMI S01, which have two production versions. I...
View ArticleDefine Receipt Elements for Receipt Days' Supply
Hello expert, SPRO --> MRP --> Evaluation --> Define Receipt Elements for Receipt Days' Supply Currently this setting is blank in Config for safety stock. Now I am setting "1" for safety...
View ArticleScheduling planned order question
Hello Experts, I'm new on PP module and I have one doubt.... When I created a planned order from a BOM material and I press shift + F6 for scheduling, some operations of the routings appears.... but...
View ArticlePI Sheet Reversal of posting
Hi Team, I would like to know you could reverse the vales you have posted in your PI Sheet With RegardsDhanush Dilip
View ArticlePI Sheet Formula for planned quantity & characteristics for plant
Hi Team, I need your help for two issues : 1. one is i would like to make a column for plant where in the PI sheet should pick up the plat from the process order created and show it , 2. I would...
View Articleproduction order
Dear Friends, Backflush indicator is not moved for so many orders in my client. EX: User created routing with backflush indicator for all components. After that production order created. When user was...
View ArticleAutomatic Capacity adjustment to another one when load is exceeds in one machine
Dear friends, How to configure the system when load exceeds in one machine ex: 200kg /day and requirement of that day is 500kg/day.Here same type of machine is available for that remaining...
View ArticleDifference between Net Requirement Calculation and Availability check
Hi all Can anyone please elaborate the difference between Net Requirement Calculation and Availability Check? As far as i am aware net requirement calculation does create planned orders and purchase...
View ArticleHow to use the net weight from mara in work center formula
hello everybody , the question is simple, how i can take the value of mara and use it in a work center formula, withou User defined fiels? thanks
View Articleassembly line wise Production
Hello Gurus, 1 - My client wants to produce 2 different products on 2 identical assembly lines (A and B).They produce 1 ton air conditioners and 1.5 ton air conditioners respectively. Both assembly...
View ArticleRecipe Issue IN CORO...!!!
Hello Experts,I have to map a rework scenario for my client who is manufacturer of paints.The requirement is like thisSuppose FG = 10 EA of paint , Bom Structure FG (10 EA) = { X(Component 1 - 7.5 EA)...
View ArticleBOM Explosion Date in COOIS Planned Order header list
Dear Experts, Have you ever used COOIS to check the BOM explosion date for planned orders? The field of BOM explosion date in planned orders is PLAF~PALTR. I do find two fields seems like relevant to...
View ArticleMPS Planning
Hello, I have some doubts regarding MPS planning. So I have some basic questions on it 1) MPS plan on single level, means it creates planned order for material which has M0, M1 MRP Type ? If yes, then...
View ArticleFollow up setting on finish-goods
Hi all, I meet another problem, for finish-goods A, we want to create on it, and sales it. But another material B is the same as A, that means in our company we can use B to replace A totally. I...
View ArticleCannot limit BOM Usage to convert Production Order
Dear Experts, In our company, we have 3 kinds of BOMs for Production - E-BOMP-BOMF-BOM For creating Production Order, especially to convert from MPS Planned Order in MD04, we only allow the F-BOM. In...
View ArticleError During Batch Derivation
Hi Experts, I am using the functionality of batch derivation . The triggering event is GR from Production. However, I am facing following problems: 1. In DVS1, when I am maintaining condition record...
View ArticleHide PROCUREMENT PROPOSALS in MRP Run Transactions (MD02, MD03)
Hi All, I have one requirement in MRP. When we MRP run thru MD02/MD03 transactions with input selection as “Display MRP result before they are saved”, user can manually create Planned...
View Article