Dear Expert ,

 

We want to feed production plan on weekly basis. But problem is that when we started feeding on weekly basis, it is allotting bucket date  on Monday to Saturday basis. But our problem,   if any month begins with other than Monday , Say for example, 1st day of July month is Wednesday , So PIR is started with Monday (dt.29.06.15) .

 

But we want to divide  the bucket as

 

1st bucket  -  1 to 8

2nd bucket  - 9 to 15

3rd bucket   - 16 to 22

4rth bucket   - 23 to rest

 

Please guide me how to resolve the problem.

 

Regards,

Amit Biswas