calculation of setup time in routing scheduling

$
0
0

Hi experts,

 

I have a query. My FG has 3 operations.

For the 3 opns, the set up time is as follows.

 

operation 10:       0.5 hrs.

operation 20:       1.1 hr.

operation 30:       2.75 hr.

 

Now when i do a routing scheduling, the system shows the scheduling results for set up time to be 0.48 days.

 

I am unable to understand ,how the conversion happens to 0.48 days happens ?