Hi experts,
I have a query. My FG has 3 operations.
For the 3 opns, the set up time is as follows.
operation 10: 0.5 hrs.
operation 20: 1.1 hr.
operation 30: 2.75 hr.
Now when i do a routing scheduling, the system shows the scheduling results for set up time to be 0.48 days.
I am unable to understand ,how the conversion happens to 0.48 days happens ?