Hi
When i create planned order with MD 11 and put basic end date as 11.03.2016 ( Today's date) and press scheduling then planned order is scheduled to give basic start and production start dates in PAST(09.03.2016 ).
I dont have setting in OPU5 to allow start in past. Basic dates are adjusted to operation start date.
Please could you inform reason for start in past.