Dear Gurus,
This is my first question in SCN. My apologies if something is wrong
We have a bigger assembly where the same component (1p1) may go across same next levels(1N1) but different phantom assy (1A1,1A2,1A3.....). So in my routing i go for comp allocation and assign a component (1p1) to an operation, the ca03 COMP alloc screen will display
Level Path Component BOM header material
4 90 1p1 1N1
4 178 1P1 1N1
So in this case when i had to assign this to one of my operation, i get confused which one of these lines to assign because it doesn't give any information about the upper phantom assy(1A1,1A2,1A3.....). . This is just a sample i am providing. The numbers are huge though.
Is there a possibility to manage this. Appreciate the reply