Hi,
we have 10 production line where 8 production line are working now, i have created one work center with 10 individual capacity for the same.
Multiple planned order generated with same one work center. Now I wanted to use CM27 individual capacity leveling for dispatching my planned or production order to my one work center as per capacity availability
i am getting error in CM27 transaction: Message no. CY379 Requirements can not be split
Note: I have not created 10 or 8 work center with multiple routing, production version scenario to reduce complexity
Is it right way doing? CM27 only for splitting?