One work center for multiple producton line with capacity leveling in cm27

$
0
0

Hi,

 

we have 10 production line where 8 production line are working now, i have created one work center with 10 individual capacity for the same.

Multiple planned order generated with same one work center. Now I wanted to use CM27 individual capacity leveling for dispatching my planned or production order to my one work center as per capacity availability

 

i am getting error in CM27 transaction: Message no. CY379 Requirements can not be split

 

Note: I have not created 10 or 8 work center with multiple routing, production version scenario to reduce complexity

 

Is it right way doing? CM27 only for splitting?