My client request is to know who person it is working in which process order.
In order to answer this request, I already did the following in SAP
a) Create a resource type 008 in transaction CRC1
b) Into the tab Capacity, create the 002 capacity in order to assign three person to that work center.
c) The HR consultant assign the infotype 0315 to this employee
d) Create the process order with the resource I create.
e) Do the confirmation with the transaction COR6N
Until this stpe everything looks good.
But.
When I open the button for employee at COR6N the system allow me to assign ANY employee not only the three I assign into the resource.
Could you guide me about what I forget to do.
The system validate the work center information into the confirmation, if the answer is YES please tell me how.