Quantcast
Channel: SCN : All Content - SAP ERP Manufacturing - Production Planning (SAP PP)
Viewing all articles
Browse latest Browse all 1791

Effect of inhouse-production time (MM02: MRP2) on production order

$
0
0

Dear ...,

 

I have a material that is internally produced. The routing contains only setup-time, which is 6 days. The scheduling margin key is 4 days.

In the material master in MRP2 view there is the field 'inhouse production time.

What is the relation between this production time and the production time specified in the routing?

 

When i enter inhouse production time  = 0, and create a production order, the system calculates 10 production days.

When i enter inhouse production time  = 1, and create a production order, the system calculates 11 production days.

BUT When i enter inhouse production time  = 20, 60, 90, or any other number higher than 1, and create a production order, the system calculates 11 production days.

 

Why does the system always add 1 production day when the inhouse production time is 1 or e.g. 99?

 

Regards,

J S