Dear ...,
I have a material that is internally produced. The routing contains only setup-time, which is 6 days. The scheduling margin key is 4 days.
In the material master in MRP2 view there is the field 'inhouse production time.
What is the relation between this production time and the production time specified in the routing?
When i enter inhouse production time = 0, and create a production order, the system calculates 10 production days.
When i enter inhouse production time = 1, and create a production order, the system calculates 11 production days.
BUT When i enter inhouse production time = 20, 60, 90, or any other number higher than 1, and create a production order, the system calculates 11 production days.
Why does the system always add 1 production day when the inhouse production time is 1 or e.g. 99?
Regards,
J S