Dear experts,
We are working on a project where the planned orders are provided by an external system, and there is a possibility to create sales orders.
My question is : Is there any possibility to block the creation of planned orders from those sales orders (when running MRP using MD02), and make the requirements generated by those sales orders consume only stock and PIRs ?
FYI, We are using MRP Type PD, and strategy groupe 40.