Simulative planned order vs Simulative dependent requirements

Hello SAP Gurus,

 

I am searching a way to know which dependent requirements from higher level were considered to generate one simulative planned order.

Do you know how SAP does to retrieve this when showing graphic of pegging requirements?

 

 

Just as example:

 

Date   MRP Element

15/06  Planned Order 1

15/06  Planned Order 2

15/06  Dep.Requirement 11

15/06  Dep.Requirement 12

16/06  Dep.Requirement 21

16/06  Dep.Requirement 22

 

When showing pegging graphic, SAP seems to know that Planned Order 2 was generated for Dep.Requirements 21 and 22.

How to know this?

 

Thanks in advance for your advice.

 

Regards,

Rudy