Hello SAP Gurus,
I am searching a way to know which dependent requirements from higher level were considered to generate one simulative planned order.
Do you know how SAP does to retrieve this when showing graphic of pegging requirements?
Just as example:
Date MRP Element
15/06 Planned Order 1
15/06 Planned Order 2
15/06 Dep.Requirement 11
15/06 Dep.Requirement 12
16/06 Dep.Requirement 21
16/06 Dep.Requirement 22
When showing pegging graphic, SAP seems to know that Planned Order 2 was generated for Dep.Requirements 21 and 22.
How to know this?
Thanks in advance for your advice.
Regards,
Rudy