Hi Team,
system is planning more qty than the demand.
Demand for goods is being issued under normal service process, but additional demand is being created when MRP runs.
NO service requirement is entered but demand is generated when MRP runs.
what could be the possible reasons which triggered this requirement ?
There is no min and max lot size defined in the material master. MTS , External procurement.
stock - 4
in PO purchase req. number is available.
in ordres -PM ORDER both are teco 15.06.2016.
best regards,
sanket.