Dear Experts,
I am in PPPI MTS environment and below is my scenario;
Finished Products F1 and F2 have same semi finished product SF.
Production of SF is done at various resources depends upon product specification (only shape of product is diff), so product SF can be produced on resource R1, R2 or R3.
Now if I want to produce F1 and F2 at same time, as per current configuration all my demand goes to SF with first master recipe available and hence only at one resource (my production versions have similar lot sizes as all resources have similar capacity).
,
Requirement -
My demand for SF should get distributed to different resources like R1 and R2 as per F1 and F2. as it currently goes to only first available production version, and I don't want to use manual selection of production version as data is very large.
Need your expert comments on this.
Regards,
Devidas Karad