Quantcast
Channel: SCN : All Content - SAP ERP Manufacturing - Production Planning (SAP PP)
Viewing all articles
Browse latest Browse all 1791

MRP Run should not consider Sales Order which is more than 60 days

$
0
0

Hi All,

 

Thanks in advance.

 

Please help me and reply on this at earliest.

 

Requirement : During MRP run the Sales Order whose delivery date is more than 60 days from the sales order creation date should not considered during MRP Run.

 

Current System Scenario : MRP Type VB (Manual Reorder Point Planning) is being used. And no Strategy Group defined in MRP view.

 

Analysis already done : Set Planning Horizon to 60 Days and run MRP in sequence on NETCH 2311 but didn't work.

 

Kindly give your solutions.

 

Regards

Anish Verma


Viewing all articles
Browse latest Browse all 1791

Latest Images

Trending Articles



Latest Images

<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>