Multi Level Subcontracting

$
0
0

Hi Experts,

 

I have the following scenario;

 

Item: FX - Made from item X

 

Item X need to go thru a Multiple Subcontractor Process to be modified to item FX

 

Subcontractor 1 - Testing - Item X Issues

Subcontractor 2 - Painting

Subcontractor 3 - Cleaning

 

I need to move item X thru the mentions scenario's.

Is there a way to do it without having to create 2 more additional material codes?

 

This is Production Order as well as Subcontracting.