Can Planning Calendar override Factory Calendar settings?

$
0
0

Hi Experts,

 

 

We have a scenario wherein our Factory Calendar(US) is having 5 days working(Saturday's & Sunday's closed) & Capacity Planning/leveling Calendar(ZB) is having 365 days a year as working.

 

MRP plans based on Factory Calendar(US) & Capacity Planners schedule their production on weekends using transaction MF50 & CM25 which basically looks at the Calendar maintained at Work center level(CR02>Capacities tab>Capacity Category>ZB)

 

Now, there is a requirement wherein we need MRP to plan only select materials on weekends & drop Purchase Requisitions on Saturdays/Sundays.

 

For that we created a Planning Calendar(PC1) via.MD25  & then maintained it in the MRP2 view of the material master.

 

But, when we are trying to run MRP ,the Order proposals are not dropping on weekends.

 

Even when we are manually trying to schedule Production(Planned Orders) using MF50,the system looks at the Factory Calendar & reschedules the Order for a Sunday on preceding Friday as the Factory Calendar(US) is only open on week days.

 

Is there any other per-requisite i need to maintain apart from MD25?

 

regards,

 

Rishi