Dear Team,
We are following MTO-Repetitive scenario. My query is, if there is a planned order of quantity 100. In MFBF, if I confirm scrap of 10 quantity, neither the planned order quantity is getting reduced to 90 nor the document with movement type 551 is happening. Please find the attachment for the movement types maintained in my REM profile. But the component quantity is getting consumed where 261 movement type is happening. But for the material which was confirmed as scrap is not saved/stored anywhere in the system and I can only see in MCP6 Tcode. Please help in knowing where I am going wrong and the table/field name where this quantity gets stored (other than S225 table)
Thankyou.
With Regards,
Rajiv M.