Hi,
My Production Order has a routing with 3 operation in which Operation 0020 is with Control Key PP02 and a got a PR for subcontracting this operation.
In ME21N for this PR Acc. Assign is "F" & Item Cat is "L" is maintained.
when i try to save the PO got an ERROR message "ME154 - Not Possible to determine any Component".
Since this is intermidate material we will not have any component to be assigned for this PO.
From SCN i got a suggestion to change this error msg to warning.
I approached ABAPer they said as "this is called by Std functional Module and it can't be changed here and if possible you change via SPRO".
In OMCQ i could not find this error msg in list.
What is the solution...
Thanks With Regards,
Dinesh V.