Hi,
In our plant X there are 100 materials (of MRP type p3 )for which MRP job run everyday. But recently what we have observed is some materials are not included for the MRP runs for some days because of no indicators(NETCH,NETPH) automatically updated for planning file entry in MD21 for some days this can be because of no demand changes, posting changes, routing changes etc. for the material.
But what I have observed is materials are included in MRP if I would do manual MRP RUN in MD02.
and materials also included if planning file entry is updated with anyone of the indicator in MD20
Actual requirement is;
Planned orders which were created after planning time fence should not be firmed until the user firm manually. So if MRP run is not including these materials for some days the planned orders are coming within the planning time fence so then user have to do manual MRP run md02 to push the planned orders out of planning time fence.
As it is difficult to do manual MRP or creating planning file entries every day So how to include the materials in MRP job run for which planning file entry is not updated as there is no demand changes.