BOM Explosion - ECN display - Assembly part number Explosion

$
0
0

Dear Gurus,

 

In one of the requirement from user we found one of the observations which is shown in picture.

 

When I am passing the from & to date of the assembly when exploding in CS03 only one ECN is shown , where as when the same is exploded in CS03 able to see two ECN.

 

My query is how can this be handled in standard process as we are in process of developing "Z" report in which user had raised that for the day if a part number is valid unable to view the same in report as the report base is functional module of CS03.

 

Pictures of the same attached as below.

 

BEFORE: Below is the step wise  exploded view through CS03 in which only one ECN is shown.

 

2016_01_20_18_33_19_Display_material_BOM_General_Item_Overview.jpg+

AFTER : Below is the depiction showing two changes made for the same part number on  from 18.08.2012 & to 18.08.2012 & again the part number is changed on 18.08.2012 till 31.12.9999.

 

2016_01_20_18_35_43_Display_material_BOM_General_Item_Overview.jpg

 

Thanks in Advance.


Vignesh.V