Dear SCN Members,
I am a part of SAP implementation project team, its a textile company for which we are configuring SAP PP module.
Mainly we have decided 3 Operations i.e. Cutting, Stiching, Packing.
BOM is single level, we are making FERT from ROH.
Here is the Condition: we do not know FERT material (Articel) to be made (like there are many types of Articles and the Article differs with different size and color combinations), the FERT (Product, in this case it is a Shirt) is getting decided while the Cutting operation, but my problem is I need to issue some quantity of ROH material (which can not be decided as the cutting operator decides the cutting of different Articles as to maximize utilization sheet of textile) for the Production to make the Cutting operation.
The main problem is the issue of the ROH material for the FERT.
I also can not make Production order as the FERT (Article) is not decided.
Please suggest how can I achieve the above.
Your reply will be more than valuable to me.