Dear all,
i have the following requirment:
Production order MTO 1 PF
Production order MTO SG
Production order MTO SG
I know very well that in the standard system is not possible to scheduling all production order without handle the combination E-52 in the master data, but i would like to know if with the custom activity is possible to do with enhancement in the COHV during scheduling activity.
Is possible to add a new funcionaluty in COHV in order to scheduling the production orders with the own logic :
Production order MTO 1 PF
Production order MTO SG
Production order MTO SG
For example to schedule the first production order , after taht the new finish basic date calculated must be the basic start date of the second production and so on.
Thanks a lot
Daniele