Dear Sir,
I would like to share a problem to get the solution.
1) Generate PIR for the month of January 2016 is 2000MT. Run the MRP and created planned Order successfully of 2000MT.
2) Convert the Planned Order to Process Order Successfully.
3) Confirm the process order using COR6 and wrongly posted 200MT instead of 2000MT.
4) Now again generate PIR for the month of February 2016 is 1000MT.
5) Run the MRP.
6) Here generate Planned order for the Quantity of 1800MT (remaining qty) and generate another Planned order of 1000MT.
Here is my question, Why the system has been generate the planned order for the qty of 1800MT as already a planned order was created earlier against the qty 2000MT.
Kindly provide me the solution how I overcome this problem.
Thanks & regards,
Koushik