Hi all. I have a few questions about the MRP results and I am a little out of my element here:
1. I was running MRP on line (MD01) with NETCH and I was able to get results in MD04. When I ran the same in background, I didn't get any planned orders for materials with a planning type of VB.
Any suggestions?
2. When we ran MD01 on line and I had an open PO for an item with VB, the planned order didn't consider the open PO. Why wouldn't it consider the open PO?
3. I changed my background job to run with NEUPL and both requisitions and planned orders display in column 3 of MD04. When I ran MD01 with NETCH, the planned orders showed in column 7 and the requisitions showed in column 2.. How can I ensure the different requirements in MD04 show in different columns?
Thanks much in advance!