Hello fellow SAP-enthusiasts!
My customer is running MRP through a batchjob and program RMMRP000 is executed correctly, but the job log contains error message:
"Error determining planning periods for calendar xxx".
I've investigated the issue and read various related topics around it. The first note which I run into was 549193
It contains a presumption that the system is using "periodic lot size", which my customer is not so I moved on to note 368079 as instructed.
This note instructs me to 1. set the planning calendar date far enough into the future (beyond the planning horizon date). 2. Reduce the planning horizon (date?).
My planning calendar is valid from 02.01.2015 to 30.03.2017 while the planning horizon value for this specific plant has not been specified.
Any ideas what is causing the message on the batch job job log?
Are there material requirements beyond the planning calendar date of 30.03.2017 or am I missing something else?
I've also checked table VBBE's furthest material availability date - 31.10.2016 and EBAN's furthest deliverdate 27.11.2015.
Thanks in advance.