Hello Experts,
We have two production versions (ver. 01 - BOM1/Rt1 (Prod. line1 )and ver. 02 - BOM2/Rt2 (Prod. line 2)) for a product line. Both have two different work centres and different BOMs.
Now system picks version 01 as a default for all planned orders created. But I need to set version 02 as a default for planned orders created (specific to some FG materials)
Planners need to create demand and generate planned orders for the entire month (in advance) in ver. 02. Then based on production plan schedule, every week production team will confirm in which prod line we need to release the production orders. Based on that planners convert the already planned orders to production orders by changing the version accordingly. (Either in ver. 01 or in ver. 02)
Plz Note: I want both versions to be active. I cannot lock any versions in material master. we are not using ECN for BOM/routing (Engineering Change Management). We are not using any quota arrangements.
Please help how to set ver.02 as default for planned orders (specific to some FG materials).
Thanks,