Scheduling date of PO in MTO

$
0
0

Running MTO scenario.

 

Case-1: Creating sales order with RLD date 5-April-2016 but order is confirming on 6th April. If I check PO in this case it is getting completed on 6th April. 6th April is Basic finish date/ scheduled end date in order. I believe this is an issue here but not sure why does it pick up 6th april even my RLD date is 5th April.

 

Case-2: Running MTO of same material but in different plant.

Creating sales order with RLD date 5th April and getting confirm on 5th April only. Even PO end date is 4th April, which make sense keeping product ready for 5th April delivery considering 1 day transit time.

 

I compared both plants material master/ recipe/ BOM - All are exactly same.

Availability check/ Strategy are same in both plants.

Even checked plant level parameters for process order type which are same in both plants.

 

I checked all possible master data/ config and compare in both plants but same.

 

So why does ATP confirm 1 day late in 1st case? where should be an issue? what am i missing?

 

Reply appreciated...