Activity Price is not capturing in process order costing view.
Dear friends, I have done all configuration and master data maintained for activity cost calculation in process order,in that only water price is not capturing in process order costing view. Please...
View ArticleCOGI- Post processing records (REM) history of deleted records
How can we know and see the history of deleted COGI records in the system. Any log and/or table that stores it.?I see in forums that AFFWPRO (Table ) is not useful!
View ArticleMRP elements (Requirements) for LTP
Hi All, Could you please let me know the MRP elements (Requirements only) that are considered for the long term planning? My requirement is that stock transport order (MRP element Ord.DS) should be...
View ArticleRouting creation from MES
Hello All, We are planning to create routing from MES and it would be sent to ECC through middleware (SAP-PI). The question really is - What is best way to create it- idoc?- Webservice if...
View ArticlePIR consumption for MTO scenario
Hi All,I know that using strategy 50 we can consume the sales order with planned independent requirements using the requirement type VSE. Is there a way that stock transport order can also be consumed...
View ArticleScheduling date of PO in MTO
Running MTO scenario. Case-1: Creating sales order with RLD date 5-April-2016 but order is confirming on 6th April. If I check PO in this case it is getting completed on 6th April. 6th April is Basic...
View ArticleEquipment Master tracking for non-serialized materials
I am looking for a common way to track shop floor work for both serialized and non-serialized materials. Equipment masters perform a great deal of the functionality I want, of course for serialized...
View ArticleCreating planned orders during MRP run
Hello. We have production version for material "A". In the BOM of "A" there are material "B", which has production version too.So we need to plan this - create recuirement for material "A". Run MRP...
View ArticleURGENT:UNABLE TO DO GOODS ISSUE IN MIGO
Hi present process order status is:REL CRCR PRC BCRQ MACM PIGN SETC *No goods issue was done to the process order(materials were not yet processed) *No confirmations were done. *NO ERRORS IN COGI...
View ArticleWhat is the difference B/w OOABAP and ABAP?
Dear All, Please explain which one we can do by using OOABAP and which one can't by using procedural ABAP.Give me better example. i know the syntax's, but i am not able to see what impotence...
View ArticleProduction order Confirmation with process message
Hi All Iam using process message PP_OPCON for doing confirmation in production order, also i have confirmation profile which is set to proposed activities. When process message is send to production...
View ArticleLTP planned order to be created with different order type
Hi All, I need your suggestions to differentiate the simulation planned order and the operative planned order. At this moment the simulation order type is same as the operative order type after running...
View ArticleScheduling Automation in CM25
Few issuesLooks like I will be able to stack more than one job per jet at a time there is nothing preventing me from doing this.Seems a bit more manual than what I was doing.How do you get it to be...
View ArticleHow Scheduling parameter start date in the past to be set for X days
Hi All,The planner is making the production schedule in ABC planning tool and transfers this to SAP.On a daily basis the planning is reviewed and rescheduled to the actual production. With the...
View ArticleIN COR6N t.code Need to change 15 actual activity
Dear Friends, In cor6n my client wants to change the more then 6 activity .if I assigned in c202 2 work center with 5+ 6 activity system throw error in cor6n‘phase/Operation in process order does...
View ArticleIndustrial waste material treatment process mapping in PP
Hello....Experts. I want to map industrial waste material treatment process in PP for my client along with CO.Client has a requirement for process based costing. The waste is received from different...
View Articledata table for mmbe
hi all, in MMBE t code we can see unrestricted , quality & reserved stock. can anybody please tell me for this tcode which tables SAP calculates ?
View ArticleWaste Material Treatment Process Mapping in PP Module
Hello Experts, We want to map waste material treatment process in PP module along with CO for my client .They require process based costing.Client receives waste material from customer and according...
View ArticleIssue with GR Qty - Batch Specific UOM
Hi, I am facing problem while posting Goods Receipt for Raw Milk in Liters as the KG equivalent is not getting derived properly. For raw milk stock keeping unit is KG and receiving unit is liters....
View Article