Two jobs run on one workcentre

$
0
0

Dear Frds

 

Two jobs are executing on one work centre , that jobs are completed in one hour

 

for instance

Two jobs have been started 8:00 to 9:00 at one work centre

how i will confirm an individual job on confirmation screen

if i enter 8 to 9 time on confirmation screen against individual job

then system will show 2 hours ,actually machine was executed only one hour

 

 

 