Hello,
We have a profile for CM25 that works OK.
Now the planners want to have this layout linked to MF50.
This is done by setting the user parameter KP2 to the overall profile.
Having done that I open MF50 and the planning board looks OK.
But what is missing is the elements in the Order Pool.
The process orders and planned orders visible in CM25 are now gone.
The two overall profiles are the same except for the control profile.
Anybody out there who are very clever with the intricacies of the graphical planning board who can say anything about the dependencies here
as to why the capacity requirements do not show?
Thank you very much!
Regards,
Tor