Hello gurus,
i'm facing the following problem:
- i have set in a WC for the scheduled capacity type 001 two single capacity (16 * 2 = 32 h)
- using co02 (or cm25), i split the order in the two single capacity
- the start date/hour is the same for the operation and the splits, but these ones should have a different finish date/hour, because the split duration is different based on the quantity and the available capacity of each split respect to the WC total capacity;
- the operation start and finish date doesn't change despite the splitting.
i was expecting that the operation finish date gets the lastest split finish date/hour, but it is not working.
I'm missing some configuration or the system behave this way correctly?
Thanks in advance.
Bye.
M.