Hi PP Gurus,
I have issue in MRP for Spares Material where no PR's are generated after MRP BG Job run.
Client wants to run the MRP via BG Job only and not ready to use MD03 or any Manual transaction.
Following are the Master data settings,
ECC6.0
MRP Type- VB - Manual Reorder Point
Reorder Point- 1
Lot Size - FX
Fix Lot Size - 1
client don't want to maintain the Safety stock .
Go-Live has been done in last month only and NO PR's are created even if Stock is ZERO.
Pl help me if any Data is missing.
Thanks in advance.
Regards,
sachin