Dear Team,
We are using MTO-REM scenario. Planned order is generated after MRP Run as procurement type maintained was 'X". Now, only half of the quantity I want to produce in house and the remaining half I would like to outsource to one of my other plants or third party vendor. When I tried to convert the planned order using MD14 Tcode it shows the error as "Planned order XXXX cannot be converted". Googled but no exact solution found. Everything should be tracked as per sale order line item only.Please help or if any link can help which was already answered, please let me know. The screen shots of my planned order and error in MD14 provided in the attachment.
With Regards,
Rajiv.