Is there anybody can help me regarding assembly scrap and
expected yield variance?
I have an issue with total quantity of production order, for example I create production order for part A with assembly scrap 2%:
[CO02]
Total Qty : 60
Scrap portion : 1
Expected yield variance : still 0 due to nothing conformed yet.
The when we release and print the production order quantity is 60.
And after some operation conform with yield 60, the production order become:
Total Qty : 60
Scrap portion : 1
Expected yield variance : 1
When we reprint this order the quantity become 61.
What should we do to make the quantity same from fresh print and reprint after confirmation?
Thank you in advance