Wrong Delivery Date of Schedule Line after MRP

$
0
0

Hi Expertz,

 

We are facing an issue in client system that system calculates the wrong delivery date for schedule lines after MRP Run.

 

 

Lets take an example,

 

Product A(Header material), Product B(Component of Header Material A)

 

I have maintained the Planned Delivery time of component B as 1 Day and purchasing processing time as 1 Day

 

Having a process order for Product A on 10th Feb 2016.  After MRP, Schedule line have been created for component B, but whose delivery date is also calculated as 10th Feb 2016

 

As per  my understanding, Delivery date of component B should be 8th Feb 2016 (10th Feb 2016 - 2 days(Planned delivery time & Purchase processing time).  But always calculating the same day as order start date.


Please let me know if I am missing any configuration for this ?

 