component allocation changed date and time
Dear friends, I have one requirement.I have one production order with valid routing.we assigned some components for the operation.This production was completed. Again the user changed the component...
View ArticleSerial Number Duplicacy for same material during MFBF
Dear Gurus, As per above screen shot for mov. type 131 in both documents 20 same serial numbers are used on same date So how it is possible to used same serial numbers again?? We have check Log in...
View Articlequota arrangement - reduced allocated quantity when creating production order
I have searched the forum and the web for this issue about the quota arrangement but the answers I found did not apply to this case.I also found 2 old notes: 710639 and 730070 which are implemented in...
View ArticleHow to delete last serial number using IQ02
Dear All, Scenario: Through Interface we push mass serial numbers from non SAP to SAP with pairing data Condition: No same serial number push from non SAP to SAP System Suppose X is material having...
View ArticleWhat's the name of the special table mentioned in note 787807?
Hi, We are deactivating release versions in ECC as per note 787807. We're interested in knowing the names of the "special table" (keeping process order data as per when the order is released) mentioned...
View ArticleImplementation SAP PP on machine building plant
Hello everybody. We are going to implement SAP on machine building plant. I have some expierence in process industry where in common we use Recipes, Production version and process orders. But in this...
View ArticleAvailability Check for Material
Dear All, I have a question on Availability check for a material.As we can see that on 22.03.2016, 4000 quantity of material is available in plant DE01.Then for the order 4500419078/00002 which is for...
View Articlerun MRP as per MRP area (storage loc) wise
Dear all I want to run MRP as per MRP area (storage loc) wise plz guide me
View ArticleSAP ECC S&OP Flexible planning
Hi Friends, I got a requirement to use SOP functionality Flexible planning, I got the steps from SCN and other forum how to configure.I am in the process, But as per requirement I need some ideas from...
View ArticleWhere is Data that automatically populates a PI-Sheet stored?
There is information / data that appears to be hard wired somewhere behind the scenes of our PI-Sheets. I did not build the Master Data info pictured below into the PI Sheet, and the data does not...
View ArticleHow do I extract Data from a table inside of a PI-Sheet
We are struggling to extract usable data from Repeated Data Request tables that are part of our PI-Sheets. Can anyone provide assistance or guidance on how to successfully extract data?
View ArticleFiltering MD16 for PlORel and PlOrd.
Hello Sap Gurus, Just wanted to ask if there were any settings in MD16 where we can specify to only display Planned Orders/PlOrds instead of both PlOrds and PlOrel (Material view)? We noticed that in...
View ArticleSTLBEZ field in production order
Dear experts, I have fews order in which STLBEZ field is appearing as blank.In most of the orders it got filled by the header material only.But now i want to update this field(STLBEZ). how can i do...
View ArticleHow this mrp run takes place,sometime customer requirement getting...
During mrp run Customer requiement are considering some time and system does not consider the customer requirement..how it is behaving erratic ?
View ArticleMass reschedule of PRs according to MRP sugestion
Hi! Is it possible to reschedule the delivery date of Purchase Requisitions massively? It could save many hours to me and my collegues. Everytime the requirement date of a top level material is changed...
View ArticleRecursive BOM
When recursive BOM flag in details view of BOM,same component does not shows the levels in cs12 during exploding,is this standard behavior of system Regards,Ajit
View ArticleHow can i check the list of ECO's has been created for single material?
Hi Friends, 1.How can i check the list of ECO's has been created for single material?2.Once i completed the ECO creation and closed it, how can i identify which ECO i created?3.How to create an link an...
View Articlesystem assigns the existing serial number to a production order
Hi, Serial numbers are generated during production order release. But now system is assigning the serial number which is used on previous order.This behaviour started recently, Please suggest. Thanks
View ArticleSlowness production order
I have a situation I am unable to find the solution: Is there a material that is a plate when I cut it, what's left haul as co-product, this plate is used in various materials, however if this plate...
View Articleplanned order conversion from planning tool
Is it possible to convert planned order to production order from CM29? I know it's not possible standard way but I would appreciate if you suggest possiblity of adding customer enhancmeent to achieve....
View Article