Production order Printout for multiple layouts
All, I have researched the forum but want to ensure if this settings would work for me. I have 5 MRP controllers who print their own production orders. All the 5 MRP controllers have their own...
View ArticleScheduled dates In Process Order
Hi, The scheduled dates in the process orders are not calculated despite the formulas are mantained at the work center. I've noticed that in the General data at the process order, the system indicates...
View ArticleProduction in other plant
Hi, My requirements are the following:- We have two FI societies: 3401 and 3402.- Each society has on Plant: 3401 - 3401 and 3402 - 3402.- Plant 3401 receives the sales orders and Plant 3401 produces...
View ArticleError during alternate UOM creation
Dear All, Please refer the below error. The unit of measure WF consists of more than 99999 base units of measure Message no. MM117 Diagnosis Each alternative unit of measure must not exceed 99999 base...
View Article2 Production Order in MD4C
Dear all I have a doubt about the displayed elements when we run report in MD4C. We have a Sales Order of 500 ST and we need to split the requierement in two different production order of 250 ST. The...
View ArticlePP02 Control Key Behavior
Hi Group,At my company we are interfacing ECC production orders with ME shop orders. In our routing operations for these production orders we have defined control key PP02, as prescribed by SAP. When...
View Articlecs15 alternative bom field is coming as blank
Hi, in report cs15 alternative bom field is coming as blank.kindly help why this field is coming as blank. Thanks & Regards Sandeep Kumar Praharaj
View Articletrigger point in routing
Hi all, I am new to trigger points. What is the use of trigger point ? and how the trigger point is useful in production side ? I have gone thru the similar scn document for trigger points but still i...
View ArticleAlternative unit of measure at operational level is creating problem in CO11N
Hi Sapients, Had created combined order A with order quantity 21.3 kg with original orders B,C&D with the order quantity 7.1,7.1 & 7.1 kg. This combined order has 06 operations. For every...
View ArticleImpact when Selecting Incorrect Process Order Type
Dear Expert,Our scenario is the following:Material 1 linked to Prod. Sched. Profile 1 and Order type 1. Material 2 linked to Prod Sched. Profile 2 and Order type 2. (no good receipts for this order...
View ArticleUOm not rounding up to 1 after implement of OSS note 359621
Hi Friends, I need help on one issue. I had issue of rounding the fraction qty of component during GI-261 movt type. I mean when for Production order I issue the quantity for component with discrete...
View ArticleProcurement type - X
Hi Gurus, I have maintained the procurement type X for a material xxx. I run MRP with Create purchase requisition mode as 1 (ie Purchase requisition). but planned order is created in MD04 . Is it...
View ArticleDelivered field qty issue in production order general tab against MB51 and MD04
Hi,I am facing one issue in production order delevered field in general tab is showing the qty as 7.590 out of total qty 11. 000 But in mb51 the material Documents for 101 movements is showing for...
View ArticleGI and GR needs same batch number
Hi All, in my project I am having one SFG & one FG. After SFG manufacturing, same is moving for packaging and again we are creating a new PO for FG material. My requirement is to derive SFG batch...
View Articlecreating production order scheduling dates are not calculated exactly
Dear All, Creating production Order Scheduling dates are not calculated exactly in discrete manufacturing as well as process industry scenario Please, give a solution. Thanks. Best...
View ArticleHow we can change the Effective parameter
Hi Gurus, How we can change the effective parameters of a standard variant (linked to ECM) for a existing production order which status is REL. Also I have a query how the standard variant is linked...
View ArticleRouting Operation Counter is Same For all operations.
Hi.I need Your suggestions,Through the Bap :: BAPI_ROUTING_CREATE' I am Creating the Routing Operations, Exactly What we are doing At Ca01.But the problem is. Please Have a look On Below Attached...
View ArticleProduction Order affect in changing the BOM?
Hi Friends,Good Day...1. If i created a Production Order on 01-Feb-2015, whatever the BOM having the parent assy is as it is and in 03-Feb-2015 if i change an BOM in parent assy what will be the effect...
View ArticleHAVING ISSUE WITH WRONGLY MADE PROCESS ORDER TYPE
I am facing issue with a process order 1833570 as this process order was made mistakenly with type ZPIM instead OF ZPI2. So what happen - after giving pallet transfer ,shipping confirm it but it became...
View ArticleProduction Process for Subcontracting Service
Hi Please Help me to find a solution for the below scenario. Client has two Company codes . both company codes manufacture customized adhesive tapes. 1. company "A" subcontract semi-finished...
View Article