Hi Gurus,
I have a problem with scheduling a huge bunch of tiny planned orders in a week and they are subjected to a lot of changes from time to time. The issue of the adjustment is that different product has different change over timing, since transition matrix and is currently not maintained due to its complexity and changes will cause a re-adjustment of timing from first order till PTF.
I would like to know if there is any more effective ways to deal with such issue. My current approach is trying to plan on excel worksheet first and translate it to SAP script to help me in sequencing, however, the issue is that SAP scrip do not recognize planned order number in CM29, it has its own ID whenever you run the script. This makes it impossible to tell SAP when (time & date) I want the planned order to be produced.
Can anyone kindly advise me?
Regards,
WyCee