Dear Expert ,
We are of nature of process industries . We want to make configuration for production booking production line wise , shift wise daily .
Presently production planning are made planning calendar wise ( K is used) in to four week . Production plan are uploaded against plan version .
12 plan version are maintained for a year ( April - March ) . For particular month only corresponding version is active . Against the plan MRP RUN is executed and planned order and PRs are generated .
Against the weekly plan , factory planner , make this plan to convert to daily and this is done off the system , and that basis , shift wise , line wise production is carried out .
We want this process through SAP Process '
Please advise how to do this process ...
Regards,
Amit Biswas