Hi experts,
Is it possible in production order change (t_code: CO02) to change the operation start dates/times of specific operations and recalculate the dates and times of the consecutive operations?
For e.g. operation 0030 has start date/time 05.09.2015 -08:30:00 and I want to change this date/time to 06.09.2015-11:30:00.
Is it possible to change the operation start date/time directly in production order change (T_code:co02)? And in a manner that the other operations are rescheduled? So when I reschedule operation 0030 start date/time to 06.09.2015-11:30 the start date of operation 0040 and 0050 should also be recalculated.
Hope you can help me!
Regards,
Nashaf