Costing variant
Hi all, Need to have clarity on the costing sheet of overhead calculation of finished and semi finished material. And assignment tab in okkn. please help me on this
View ArticleDependent Requirement
Dear All I run MRP through MD51. Planning result was Pur Req -16, pld order-21, dependent requirement - 52. As per my knowledge Dependent requirement should be 16+21 = 37. If i am wrong...
View ArticleSpecial stock indicator in sub-con P.O 'E'
Dear Sir, Please can you elaborate how system will trigger special stock 'E' in sub-con P.O. Regards,Pralhad
View ArticleData extraction for Batch costing...!!!
Hello Experts,I am working on a batch costing project and need your help.I need to do to valuation of every batch for analysis, currently in system i am following below methodTotal Actual Cost = 6916...
View ArticleMRP Planning File
Hi,When I am running MD01 the purchase requisitions are not created...But when I run MD02 it is working fine... When I checked MD21 for planning file entries... i found that the entries are created but...
View ArticleCapacity Requirement using finite scheduling
Dear All, On any work center (labor oriented), if one particular person is absent on any particular day, System should reflect his absence to the work center. Hence available capacity has to be...
View ArticleChanges in production order
Hello, Could you please explain how i can see changes made in production order and who made them?Best regardsM.
View ArticleBOM item user exit
Hi, I have got one user exit "PCSD0002 BOMs: Customer fields in item" for adding valuation type field in BOM at item level.I just wanted to know that whatever valuation type will be given here for BOM...
View Articleactivity confirmations are not updated in production CCs
Hi Gurus Problem : I created a collective production order with automatic goods movements . There are 3 POs including the leading order. I confirmed the all the POs using CO11n . All the goods...
View ArticlePlanning strategy 40
Hi, I am testing planning strategy 40 and here is the scenario Avl Stock 200 GALPIR: 300 GALSales Order: 600 GAL When I ran the MRP the system proposed a planned order for 400 GAL and the entire PIR...
View Articlelot sizing procedure
hi gurus , when creating material master for material type "fert"I am getting the following error pl resolve urgently *Enter a valid lot size (materials planning)**Message no. M3497*...
View ArticleWater as a material at 0 cost
Dear experts, For a new manufacturing process, the business requirement is to have water created as a material at cero cost, with QM active (so quality inspections can be created) and to be able to...
View ArticleEDITING PLAF TABLE
Hi experts, I'm trying to set or change the data in the fields named AUFFX, PEDTR, PSTTR in a planned order, on transaction MD12.I want to make multiple changes in different planned orders, in PLAF...
View ArticleSome parts in the BOM are not updating/showing in costing structure BOM...
Hi, Some parts in the BOM are not updating/showing in costing structure BOM eventhough after its ran for costing BOM, please suggest me what i'm missing? Regards,Santhosh.
View ArticleProduction BOM change automatic notification to costing team.
Hi, Once i changed the production BOM, How costing team gets automatic notification that BOM has been updated/changed? So that costing team again re-run/re-cost the BOM... Regards,Santhosh.
View ArticleMRP Planning File
Hi,When I am running MD01 the purchase requisitions are not created...But when I run MD02 it is working fine... When I checked MD21 for planning file entries... i found that the entries are created but...
View Articlerouting group counter
Hi, Can we assign common group counter to common routing group. Say for example if one material code A0001 has routing group as 50000001 with group counter as 1 and other material code A0002 has...
View ArticleLTP Process in SAP
Hi,In LTP process, We follow the below steps. Creating and releasing Planning scenario.Corresponding PIR creationsLTP runMS70- set up purchase info data with source versionMS71- copy of Purchase info...
View ArticleUnits of measure of activity type is wrong while confirming through CO11N
Hi all,I’m have some issue with unit of measure after confirmation. I have a production order with 6 operations 0010, 0020, 0030, 0040, 0050 and 0060. Operation 0060 marked as milestone. When I...
View ArticleZero records converted in RMCA9155
Hi Experts,I am trying to execute program RMCA9155 for MPS process, to Copy and Delete version 000 to a Week Source info structure S901Source version 000 Target info...
View Article